According to Law no. 169/2026, published in the Official Gazette on August 10, 2026, the Code on Territorial Planning, Urbanism and Constructions ("Urban Planning Code" or the "Code") will enter into force on August 25, 2026, and its application is not conditional on the adoption of secondary or tertiary legislation. As of that date, Law No. 350/2001, Law No. 50/1991 and certain provisions of Law No. 10/1995 will be repealed.
Among the most significant changes introduced by the Code are:
The Urban Planning Code maintains the building permit as a general rule for new construction works, intervention works on existing buildings and landscaping works, introducing exceptional cases in which the works can be carried out based on the simplified notification procedure or, in certain cases, without any prior formalities.
The notification must be sent to the competent local public administration authority before the commencement of the works and shall include:
The form and the project can be submitted in written or digital format. The competent local public authority may:
The categories of works eligible for the notification procedure are expressly listed in the Code. Requirements relating to construction quality, environmental protection, urban planning regulations and cultural heritage protection remain fully applicable.
For example, certain interventions on existing constructions outside protected built-up areas and areas of protection of historical monuments may be carried out without a building permit and without prior notification, provided that the works do not affect the essential elements of the building or alter its legal status.
A regularisation permit may be requested where construction works have been carried out either without a building permit or in breach of an existing permit. Under the Code, such a permit may only be issued for:
For all other categories of buildings, the Code provides for a one-year period during which regularisation may be sought. Upon expiry of this period, no legal mechanism will remain available to legalise constructions erected without a permit or in breach of a permit. Obtaining a regularisation permit does not eliminate liability arising from the unlawful execution of construction works. Constructions that cannot be regularised may ultimately be subject to demolition or removal measures.
For projects underway on August 25, 2026:
Nevertheless, a case-by-case assessment is advisable, particularly where the authority competent to issue the relevant permit changes under the new framework or where certain approvals are still pending.
Source: [Law no. 169/2026 on the Code on Territorial Planning, Urbanism and Constructions, published in the Official Gazette on 10 August 2026]